Method of findingthe dry ingredient quantity of 1 m3
concrete.
Answer Posted / b.santosh kumar
you have to take 1.52 as constant for calculating concrete
mix ,let me explain it this 1.52 is the quqntity of total
dry aggregate which is required.so when ever u require to
know the quantity for any given mix .u need to add up the
ratio of mix and divide 1.54 by the sum of mix ratio u ll
get the quantity of cement for one cum
eg: suppose m20 mix u need to calculate the concrete then
simply add the ratio of m20 i.e 1:1.5:3 so the total is 5.5
and divide 1.52 by 5.5 u ll get 0.27 cum of cement which ll
b required for 1 cum of concrete and if u multiply it(0.27)
by 30 u ll get the no. of cement bags .follow the same rule
for diff type of mix
Is This Answer Correct ? | 340 Yes | 77 No |
Post New Answer View All Answers
What is the meaning of a blue land surveyors flag?
how to calibrate the RM 800
How many square meter can a worker/labor demolish a structure per day?
five benefits of using standard terminology in the measurement process
if mineral admixture add into concrete then what is the differences between full cement concrete & fly ash added concrete of their SP. Gr.?and for the changes of SP. Gr. what is the changes in concrete
What do you mean by the word 'shear'?
satart to end steps by step process of building construction...? i want to planning theme accuretly
i am completed my b.tech EEE in 2009,,,iam trying the job 3+ for AUTO CAD (ELECTRICAL),, what is the market for autocad electrical in hyderabad... how to handle the intervws give some suggestions ?
List out some of the software used in the construction sector to estimate cost and monitoring expenses?
hii.plz send me hpcl placement papers for officers trainees for graduate engg plz my email id is ajm_knit@yahoo.com
(Project Management Topic) What are the important criteria in the successful realization of the project?
Design a built-up column carrying an axial load of 1200 KN. Its length is 8m and it is effectively held in position at both ends and restrained against rotation at one end. Assume yield stress of 250 mpa
IS code for Rolling Margin of steel
Sometimes the side of concrete bridges is observed to turn black in color. What is the reason for this phenomenon?
What are the delays in construction projects due to approvals from owners? How can we analyze them in different prospective? Whats their affects and effects on presently going work?