1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement
Required? Brick Size 9" 4.5" 3"

Answer Posted / arunava singha

brick size in meter=.23*.115*.075 =.0019
add 10 mm mortar for ech sides=(.24*.125*.085)=(.0025)

bricks required for 1 m3 =(1/(0.0025)=400 nos

mortar required =(.0025-.0019)*400=.24

add 15% for wastage = (.24*1.15)=.276m3

so required sand is =.276 m3

cement is =(1440/6)=240*.276= 66 kg

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

on what basis the partial factor of safety are decided? form the load combinations

1809


(Project Management Topic) What are the important criteria in the successful realization of the project?

1666


Civil engineering related

1522


What are some structures that may be subjected to fatigue?

661


What are the Types Of DPC and its Thickness used?

961






Reinforcement details at hinged joint

2693


Material calculation of cm 1:6 for 1sqm

1506


Kindly post me previous year interview questions with answer for post of Manager (civil engg.) for NTPC, IOC , GAIL etc. I have interview on july 2013.I will be very grateful to you. Please guide me.

1796


hi, i am appearing in HPCL(CIVIL ENGG.)exam. plz send me placement paper of this exam if u are having

2043


what are the layers of the national and heir aprox thickness??

1601


IS code for grade of concrete for bamboo lintel????

1692


at which depth the construction of tunnel is economical from cost and engineering aspect.

1314


how to check and keep control on the wastage of material at site

1860


what is the use if we fixed butterfly ties in column and masonry work joint?....where we have to fix(distance)..

2043


What are your future hopes for this job?

1843