how many pcs of steel bundule in all dia 8,10,12,16,25,32,40
please how many pcs in bundle of packing??
Answer Posted / shekhar kundena
Approx One bundle weighs 50 Kg to facilitate loading and unloading. Hence, in a bundle of
8 mm : 50/(12.19 x 0.39) = 10 Length (1 Length = 12.19 m)..... similarly,
10 mm : 08 L
12 mm : 05 L
16 mm : 03 L
20 mm : 02 L
25 mm : 01 L
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
yasser arfatcompleted his degree in civil from which university
Curing time for 1)R.C.C slab 2)B.W 3)Plastering
in 2 way slab can additional compressive reinforcement can be provided if yes than in which conditions it is required ?
The properties of concrete HA-30 and how does it differ with M 30 (specify the important characteristics like workability,strength,mix design,slump test value)and what is the standard relating to it
) Design a gussetted base for a column section consisting of one sc 250 with two cover plates 300 x 25 mm carrying an axial load of 2500 KN. The S.B.C. of soil is 250 KN/m2 and the permissible bearing pressure on concrete is 4000 KN.
if we know load bearing capacity of the soil and building load falling in each footing, then how to choose the type of foundation??? and if it is shallow foundation then which type of shallow foundation should be choosen i.e either strip or isolated or raft or combined or cantilever footing???????
What is the zero value in quantity surveying
What is zoning permit?
What are the different types of civil engineering?
How to calculate paint drums per meter square
give me the rate analysis for Bituminous Macadam and SDBC
Cut Linten (RCC-1:2:4)on 10" wall - what should be the width and hight of cut Linten? Secondly, 1 X 1.6 foot,4" thick window sun/rain shed (Chajja)should consume steel,Cement, sand and Stone chips?
What are the advantages of building a dam on the river nile?
50 acre of land to be reclaimed for an average height of 2.5 mt. Dredging area is 500mx200m size. what is the dredging depth required to reclaim the area?
what is the method used for marking of cantilevers in hirise buildings by using theodolite