I am working in a process industry, in that there are
several sections devided in the SCADA screens and
individual sections may START independently. But sometimes
i am facing problem i.e, if section 2 Stopped by the
operator immediately Section 1 or Section 3 or Section 4 is
getting stopped can you expain the reason behind this?
Answer Posted / jitendra chauhan
following problem may:
1. Is same interlock may used other sections?
2. have you checked stop command DO of all section, may that same DO?
3. may network getting stop, may PLC going to stop while given to stop command?
4. may that same stop command linked on SCADA?
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
how to calibrate mass flow meter (Coriolis)? Example calibration range: 0 to 2500 kg/hr line size 3" fluid: Etheline glycol (MEG)
How to decrease opening & closing time of on/off valve?
in valve is constructed as per SME B 16.34, then which standard is used for fire testing of valve?.
what is isloted barrier how it works and what are the main purpose.how it make safe area.
What are the key features of a Distributed Control System? describing the various layers (sensor through to business system interfaces) as well as the hardware, software and security aspects of the DCS.
what is effect of specific gravity in differential level transmitter , explain formula related with this .
What are the types of valves?
What are primary elements of measuring pressure?
Difference between 2-Valve Manifolds, 3-Valve Manifolds and 5-Valve Manifolds 3 with diagram
what is KV and XV valve
What is Positive Calibration and Negative Calibration?
all types instrumentation questions want
Where are oxygen analysers installed in cfbc boilers? What are their usual readings?
What is the Working principle of Dozing valve?
i am preparing for BARC ,so plz mail me how to prepare for BARC. ALSO IF POSIBLE SOME RELATED QUESTIONS. MY MAIL ID IS khushi_4uall2003@yahoo.co.in