how to calculate no. of cement bags consumed in 1:4 and 1:6
proportion RR Masonary and the quantity of sand also
Answer Posted / sudhir pawar
Part A : The data :
Cement: 330/bag
Rubble : 2562/brass
Labour :2200/brass
Sand 6500/ brass
You already know that : I brass = 100 Cft
Desired Profit 25%
Specifications :
Rubble masonry Width 18″ to 36"
for wall compound ht upto 3′ from ground level
in cement mortar in ratio : ( 1:5 )
Material for 1 cum:
Cement : 330*(0.45*1.57*28.8)/6= Rs.1119
Sand: 6500*0.3529*5*(0.45*1.57)/6= Rs.1350.50
Rubble: 2562*0.3529*1.45 = Rs.1311
Labour : 2200*0.3529= Rs.776
Total: Rs.3756 RS. 4556.50
Profit:Add@ 25%: Rs. 1139.13
Total: Rs. 5695.63 Rs/cum.
Is This Answer Correct ? | 2 Yes | 6 No |
Post New Answer View All Answers
I want to know the relevant IS codes of practice which deals with different testings of cement-sand mortar (nominal mix)that is being normally used for brick work or plaster work in the construction work.
What is the use of extend command?
What is a tensile strength? What is the tensile strength of wood?
What are segregation and bleeding?
What is the cemnent ratio
400 ku d/c clearess ketan hota hai?
What is the difference between yeild strength and compressive strength of steel???
What is construction mitigation management?
what is differences between ferrock and concrete ?
What is the biggest dam in america?
how clculate excavated or backfilling quantity by simpson's rule
Used Cement & Sand in 1 Square Meter or 1 Square Feet For Brick Work 0.115mm ? (1:4) (1:6)
What is binding spacing of the rebars at lapping zones.
GIVE US DETAIL OF YOUR PRESENT EMPLOYMENT STATUS?
Steel requirement in kg of 6" thk slab Total qty 32.64 m3 Beam / column qty 35.39 m3