1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement
Required? Brick Size 9" 4.5" 3"
Answer Posted / sulaiman
volume of 1 brick = 0.2286*0.1143*0.0762= 0.00199103 cum
consider 1" thick mortar on either sides
volume of 1 brick with mortar = 0.2413*0.127*0.0889= 0.00272435 cum
No of brick work for 1 cum with mortar = 1/0.00272435 = 367 bricks
No of bricks without mortar for 1 cum= 1/0.00199103 =503 bricks
volume of mortar = (0.00272435-0.00199103)*367= 0.269 cum
volume of mortar in dry condition= 0.269*1.33= 0.358 cum
Cement required= 0.358*1/7*1440= 73.64 kg= 1.473 bags
sand required= 0.358*6/7*35.3357= 10.84 cuft
Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
Currently my house construction is going on but we just realized that the portico earth beam couldn't connect with the original earth because the beam rod not extended so Please advice
five requirements of infill panels for walls?
A super elevation of 60 cm has been provided on a 8m wide road and a curve of 260m radius .calculate the max.speed in km/hr of the vehicle that can be negotiated safely? Plz answer with full solution.thanx
how we check the thickness and line of ceiling plaster.
How much wastages taken in 1. cement 2. steel 3. fine aggregate 4. coarse aggregates (10mm, 20 mm)
WAP to print 1) 1 1 1 1 1 1 1 1 1 1 2) 1 2 3 4 5 6 7 8 9 10
dialation means
how to calculate freeboard in under ground water tank and technical details
I just got a first job in Maharashtra and m a fresher. My task is estimate the cost of excavation of earth with J.C.B. can anyone tell me how to do this??
what is labour consume factor in residential projects
how will calculate 4"thick solid block quantities 1m3 sand cement ratio and breack up detail
length where bent up is made in slab of bridge from one end
WHAT IS THE % OF CONCRETE WASTAGES PERMITED IN A LARGE PROJECT ? AND WHICH IS CODE TO BE REFERED.
What is rate for brick masonry work of 1.0 m3 in cm 1:6?
The mixture of different ingredients of cement is burnt at?