Answer Posted / hariskumaar
The first process in MRP is the checking of the planning file entry.
The planning run and the scope of the planning run (which materials are planned in which planning run) are controlled by the planning file.
The planning file contains a list of all materials relevant to the planning run. As soon as a material master record is created with MRP data and a valid MRP type, this material is then automatically included in the planning file.
During MRP run at plant level system checks for the materials which are having indicator activated in planning file and plans those materials and will not plan the materials for which this indicator is not activated….this reduces the run time of the MRP..
Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
How did you configure the payscale structure?
IM GOING TO GO FOR AN INTERVEIW SOON AND I WANT TO KNOW WHAT SAP PP INTERVEIW QUESTIONS ARE LIKE. I DONT HAVE A REALTIME EXPERIENCE THOUGH. ITS MY FIRST TIME
How to create object dependencies in a bom for a configurable material?
What is the difference between stock transport order and stock transfer order?
What is plm (product lifecycle management) in sap pp and what is the use?
What does a PP Consultant do in his/her real time?
What is 'capacity planning'?
Mention what is the purpose of using capacity planning?
Explain why there is need of production version?
What are some important tables used in pp (production planning)?
Explain what happens to planned after it has been converted into production order?
Explain source inspection.
What is SOP and types of SOP?
Tell some standard order types and what configure done for current project
Mention what is the production process in sap?