If a load test has to run for 4 hours with 2,000 users, and
the average iteration completes in 10 minutes, how many
transactions will run per minute? can any give the calculation
please.

Answer Posted / sharmila rahman

Time taken for one iteration to complete = 10 min
No of iteration completed in one min(1 User) = 1/10 = 0.1
No of Iteration completed by 2000 users in one min = 0.1*2000 = 200

Is This Answer Correct ?    12 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What are the 5 icons appear in the buttom of the controller windows?

606


What are the capabilities exactly you look for while selecting the performance testing tool?

606


What is vuser-end section?

636


How do you load a load runner agent?

658


What is manual correlation?

661






What is the basic credentials should be provided while recording SAP-GUI?

2725


What are the four selection methods when choosing data from a data file?

710


How you set maximum number of vuser that a host can run?

638


How does loadrunner execute a performance scenario?

629


What is performance testing in loadrunner?

579


What is a correlation? Explain the difference between automatic correlation and manual correlation?

627


How do you enable text and image checks in vugen?

594


What are the different types goals in goal-oriented scenario?

566


While scripting you created correlation rules for automatic correlation. If you want to share the correlation rules with your team member working on the same application so that he/she can use the same on his workstation, how will you do that?

666


How can we develop the database vuser script?

587