Method of findingthe dry ingredient quantity of 1 m3
concrete.
Answer Posted / mufaddal hamdard
1.5m3 of dry material is required to get 1m3 of concrete.
and 2% or 5% is the amount of waste taken in account
1.5 + 0.02 is 1.52
or
1.5 + 0.05 is 1.55 thats it.
and now how 1.5 is derived is the question
As it is considered that when materials are mix in mixer the voids are finished after mixing and the output is 67% of the input in mixer
so
1/.67 is 1.5
Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
how much tempareture are required to make liquid state of pid leed
For a washout valve why are two gate valves required in normal practice?
Define polar co ordinates.
Which tests are performed on soil to decide the type of foundation to be provided.
what is work of planning deptt. in any construction compny (in road project)
How much material will consume for following specification water tank (9*7.5*6 feet)?
Why Vitrified tile are getting pop up.
how statics is different from dynamics
how i convert mm into standard wire guage (SWG)no.
Which stone is best for wall construction Laterite Stone or Cement Blocks
can you give me the details of rate analysis of steel and concrete?
In the design of bridge arguments what considerations should be made to select the orientation of the wing walls?
What is chemical composion test
the volume of cement req for 70cum of brickwork in 1:6 cement mortar is approx is equal to 3cum 5cum 7cum 1ocum
What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.