Lap length may different for FE 415 and FE 500 Steel, If
different what is the different, In which code is mentioned
Answer Posted / akram
In General Practice, Lap Length is depending upon the grade of concrete & diameter of he bar which we are going to used for lapping.
It is usually taken 36d for M40 , 46d for M35 , 49d for M25 & and normally used as 50d
| Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
VAT and CST ? Which benefits for buyer ? Why benefits?
calculate the quantity of cement ,sand,bars and aggregate used for 28*4 ft with 4 inch (125mm) thick
Calculation of curtain wall of box culvert
What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.
Which code is used for tor & tmt steel bar?
Define block?
In the present situation of ban on mining sand from rivers,can we go for formation of earth dam filters viz;Horizantal sand blanket,inclined chimney and filters under rivetment with crushed rock sand of 6mm down size.If so what are the specifications and is there any codal provision for its authentication?
What is the difference between linear dimension and aligned dimension?
Explain what is change order request?
may i know the detailed description of cutting length
What is an object snap mode?
4. Differentiate between NC and OC soils. Draw curves for (i) Stress vs Strain (ii) Volume charge vs Strain (iii) Pore pressure vs Strain for these soils
How much cement,sand,bricks and water needed for 1square metre brick work?
what is the use if we fixed butterfly ties in column and masonry work joint?....where we have to fix(distance)..
how much st. steel is required for staging of concourse slab of a elevated metro station allowing through traffic .