Answer Posted / z.m mughal
M25 = 1:1:2
10.87 bag/m3
Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
what is the sequence of the activities in the typical under ground water tank including civil & MEP works.
How to calculate the quantity of ingredients of M20 grade concrete?
How to calculate the cement plastering for circular and rectangular water storage tanks and how to calculate the area of circular and rectangular floor?? Please help me
What is the frequency of sampling for the materials of cement,Fine aggregate, Coarse aggregate .and refer which code
What are some structures that may be subjected to fatigue?
What is the per cu. mt. price of ready mix in Gujarat region.?
List out the types of roofs?
What are the different theories of failure under static load?
please, what is the required bar for a column of 6mx6m the dept is 405mmx300mm,its an axially loaded ?
what are the Task work of different labour.?
what is the list of building construction equipment & teir output?
Can a wave happen in the middle of the ocean like in the movie poseidon 2006?
Required amount of Steel bars, cement/ square feet for roofing of residential building upto 3rd floor.
what is called the inverd level of mabhole chamber?
Analyze the rate for 1st class brick work in superstructure with 1:6 cement sand mortar. Consider 1000 cu.ft quantity and work out the rate per cu.ft