How to make a Budget?
How will the user find out whether the purchases are under Budget value?
How to take out project cost report?
Answer Posted / sapmmgopal@gmail.com
Budget of Purchase Order can be routed through Internal orders.
The Process is
1. Created Project
2. Created WBS
3. Add budget to WBS and release it
4. Create Internal order and assign the WBS to it
And now you can use this Internal Order in your PO against the Item category F or K (as per your PO requirement).
User can run CJ31 with WBS element and analyse the PO/PR/Consumption against the WBS element.
There are several transactions to take the project cost.
KOB1/S_ALR_87013003 as the best.
GopalK
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
Outline 'stock valuation methods' for material revaluation?
What are the initial configuration steps for inventory management?
Explain the 'inventory management' sub module?
Purchase group is assigned at to which organization element? Plant or purchase org or company.
What are the important fields in purchasing view?
What are the variousfeatures of consignment stocks?
If the recruiter is expecting thorough Knowledge\exp on the following topics:- o Material master o Vendor master o Purchasing o Release strategy o Inventory management What type of questions can i expect ? Please mention some important questions
How to handle free items in po?
What is the procedure to make the period indicator in the mrp2 view as āpā?
What do you mean by reservation?
What are the main master files used in mm?
Explain mrp type
How are the consignment stocks created?
Explain the 'storage location' in sap?
Is material and vendor data available at all organizational levels?