What is Current Shuttering rate (labour + materials) for Columns, Beam & Slab on Item rate basis ?

Answer Posted / javeed

Rs. 200.00 per Sqm (clients shuttering and)250.00 (with out client shuttering)

Is This Answer Correct ?    7 Yes 16 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

how much cement is consumed by a stone masonry wall 17.7m long,0.55m wide and 1m high

1429


what is the use of beam end forces while using a staad ? wha they are show

2476


qty. of cement & sand required (100sq.mtr) for fixing of floor and wall tiles also fixing of marble stone on the floor

1752


Concrete cover for slab, column, beam and footing?

640


std penetration resistance in very stiff clays lies bet 2 & 4 4 & 8 8 & 15 15 & 30

1608






In cement making,what is meaning of blend,fineness,density. 

2978


What are the different types of foundation?

717


Name the main components of a cad gui?

1036


I Want To Know Quantity of Cement Conc. & Sand in Column of 9"x9"x10'

2041


While calculating the weight of the steel per running meter, the formula used is [(dxd)/162]. Why 162 is used in denominator & how it is derived?

1130


Give list of building construction equipment & explain about them in brief. How much is output of JCB, POCLAIN, Steel cutting & bending machine, material hoist, tower crane?

2594


HOE TO YOU PLAN TO ACCHIEVE THE GOALS?

1673


If we don't have drawing for Excavation of building,At what rule we will go for excavation and how much depth will go for a villa?

1259


What is the Tor steel Consumption for residential building G+24 footing (thum rule) ?

1392


How much quantity water should be placed in one cubic meter area?

892