1 Cum Brick Work CM 1: 6 - How Many Bricks ,sand,Cement
Required? Brick Size 9" 4.5" 3"
Answer Posted / nabakumar
Without Mortar 1 brick volume = 0.23*0.11*0.070 = 0.0018
Brick Required for 1 Cum. = 1/0.0018 = 555 Nos
Cement Mortar Ratio - 1:6
cement required for 1 cum = 6+1 = 7
1/7 = 0.143 cum
0.143*1440 = 205.92 Kgs
Say 206 Kgs = 4.12 Bags
sand Required for 1 Cum = 0.143*6 = 0.858 cum.
Is This Answer Correct ? | 0 Yes | 3 No |
Post New Answer View All Answers
silt%= silt volume/ silt+sand volume is this right?
Can a wave happen in the middle of the ocean like in the movie poseidon 2006?
What is type failure of road surface? how to repair the failure of road surface?
how to calculate weight of 1.8 cum of aggregate
Mention what are the composition of a landfill?
What is Grid floor and mention its advantages ?
a) we have 30nos., 300mm dia, 4m length double under reamed piles.calculate excavation quantity.b) tell concrete qty. also.
i need the syllabus for the direcr recruitement of executive engineers in andhrapradesh
if we use 1.25 bag of cement 3 pharma metal and 2 pharma crush sand what is the strenghtexpected for RCC column
What are the different types of foundation?
In few lines, please be elaborative on extras and talents that make you a potential candidate for the post:
what would be the design load of R.C.C Cooling tower per cell.?
how to calculate the dry wt of sand and cement for a required design mix?for ex:M20
What are the methods in tiles flooring ? What are the methods in brick work? What are the methods in plastering ? What are the methods in wall tiling?
How you read 5x3x1 #4 @ 20" 0/C in steel structure?