HOW we can calculate the quantity of sand and cement for 1:4
plastering with a thickness of 12 mm..total area need to be
plaster is 985 sqm
Answer Posted / ashish
Area to be covered 985 sqm
thickness = 12mm
total cubic meter of work to be done = 985*.012 = 11.82 cum
cement sand ratio = 1:4
Cement to be consumed i Volume = 11.82*1/5 = 2.364 cum
Weight of Cement used = 2.364 * 1440 (density of cement) = 3404kg
no of bags used = 3404/50 = 68 bags (approx)
Is This Answer Correct ? | 4 Yes | 0 No |
Post New Answer View All Answers
How much quantity water should be placed in one cubic meter area?
Caching, Multithreading and RAMBUS are 3 methods for resolving the Bottleneck problem. Please give an explanation for each one (how are they resolve the problem?)
How do you measure concrete?
Is it possible to make a feature using an overdefined sketch?
Define What are the uses of alloys in daily life and how are alloys made?
How many days should curing of plastering, brick work and concrete
Which ratio use for cement selery???
1. What is coefficient use for calculation of shuttering. 2. What is coefficient use for calculation of reinforcement in one cum of concrete.
what is the clear cover for shearwall?
WHAT THREE SPECFIC JOB POSITIONS TO YOU TARGET FROM THE COMPANY?
can we make bricks using m10 grade cement concrete and what would be the ratio of raw materials used and price per brick ?
flow of fluid takes place viscosity compressibilityu surface tension deformation under shear force
What is specific gravity???
In foundation design, while we do the base pressure check, we normally check if the attained pressure value is less than the GROSS BEARING CAPACITY of the soil which is the sum of net bearing capacity of soil and the overburden pressure. Actually, the overburden pressure acts against the net bearing capacity of the soil and I feel that we are actually increasing the bearing capacity value and doing the check. I feel that this is NOT right. Please clarify on this.
plumbing CPVC fitting FTE Brass full form