HOW we can calculate the quantity of sand and cement for 1:4
plastering with a thickness of 12 mm..total area need to be
plaster is 985 sqm
Answer Posted / ashish
Area to be covered 985 sqm
thickness = 12mm
total cubic meter of work to be done = 985*.012 = 11.82 cum
cement sand ratio = 1:4
Cement to be consumed i Volume = 11.82*1/5 = 2.364 cum
Weight of Cement used = 2.364 * 1440 (density of cement) = 3404kg
no of bags used = 3404/50 = 68 bags (approx)
| Is This Answer Correct ? | 4 Yes | 0 No |
Post New Answer View All Answers
which is the cheapest type of flooring (say for using for 6 months in a factory building & dismantling it)?
how can we calculate steel value, depending on load
sir tell me the formula for calculating the volume of 380mm dia double under reamed pile of 4.0 mts depth.
Design a shear wall of length 4.20 m and thickness of 250mm subjected to the following forces.Assume Fck = 25Mpa and Fy = 415Mpa and the wall is a high wall with central part 3440mm x 250mm and two 380mm x 760mm strong bands at each end with following loading. S.No. Loading Axial force Moment Shear 1 DL+LL 1950 600 20 2 Seismic load 250 4800 700
Which is the direction of negative angle?
In which code the the maximum height of concrete casting has been explained
what is the ingredient value of 40mm and 20mm aggregates?
In cement concrete how to check a quality of material also proportion of material at site ?
In the different classes or grades of concrete, what is the difference between C20, M20 B20. what are the letters C, M, and B stands for.
How to check slab shuttering level.? Or check list for slab ?
How to calculate paint drums per meter square
i need gate exam civil engineering question papers with answers
PCC Road Min Grade M 30 for VR standard Mahatashtra load 30 KN. what should be thickness of pavement, width 4m what should be length of panel.
design the irrigation canal(b,B,h )head is 3tms of water is supplied to the 200hectars of area and the base period crop is 150days dance to water travels as 35km.the canal section is trapezoidal and also calculate the slop the canal
Can any body help me out by telling hoe swelling pressure test of soil is carried out ? some body told me the procedure & formula (change in length /116.3*100%) but still i am confused ? pls help.