What is the procedure of Waterproofing in toilet sunken area ?
Answer Posted / bimal chettri.
First The Sunken is slab to be cleared from all loose
materials and it is to be coated with SIKA/Dr. FIxit water
proofing liquid. After that 1:2 CM plastering is to be done
and then the remaining area is to be filled with brick bats
and after that 4" PCC (1:1.5:3) is to be done with 10mm down
aggregate and after that Tiles work can be carried out.
| Is This Answer Correct ? | 16 Yes | 2 No |
Post New Answer View All Answers
I want to know the relevant IS codes of practice which deals with different testings of cement-sand mortar (nominal mix)that is being normally used for brick work or plaster work in the construction work.
What are segregation and bleeding?
What will you do if you encounter problems like accidents?
minimum number of bars in a beam? minimum and maximum column size and beam size ? minimum and maximum aggregate size used in multistorey residential building for columns,beams,slabs?
Explain what is Critical Path Method (C.P.M)?
Why steel rods are produced only in even dimensions?
Define What are the materials used in building a gravity dam?
what is moment-curvature relationship in semi rigid connections??
What is the yield of 100 litres of water and 10 kg of cement in grout mix?
What is the difference between yeild strength and compressive strength of steel???
Under what circumstances should pot bearings be used instead of elastomeric bearings?
if dia of inner circle is 42 m and depth is 1.5 m and width is 1 m ,then whait is the quantity of steel?
find the discharge of water through a horizental venturimeter having 400mm dia at the inlet main and 150mm dia at thorat.if the diffrential gauge between inlet and thorat shows a pressure head of 25cm mercury. assume coefficient discharge 0.98 and specfic gravity of mercury as 13.6.
what is the cost differene of a same structure when it is constructed with brick masonary, and when it is constructed with concrete as a frame structure.????????
How to take labor charges for construction of 1cum of concrete?