Answer Posted / rajesh.d.v.s.p.
normal design per square meter of slab we take 15kg of steel
hear thay given 100 sq.ft
1sq.ft = 0.0928sqm
100sq.ft=.0928*100=9.2 sq.m
total steel requried = 9.2*15=138 kgs
| Is This Answer Correct ? | 8 Yes | 8 No |
Post New Answer View All Answers
What is meaning of tlc
Can any body help me out by telling hoe swelling pressure test of soil is carried out ? some body told me the procedure & formula (change in length /116.3*100%) but still i am confused ? pls help.
what is constat for brickwork
How to calculate unit weight of concrete for m40 grade.
How to find out kg per Sft ?
Why Is Propping Required For Long Structures Once The Form Work Is Removed?
20 mpa what is the quantity of cement sand and aggregate in one cubic meter of pcc non rainforcement concreate kindly answer including formaula thanks
in the earthquqke the profile of water on dam is parabolic or not
roll of DLC in road constructions
How to calculate dry of volume of concrete constant?How it comes 1.54 or 1.57
what does the grad of cement shows (denotes)?
What is the average density of soil?
What is the basic difference between OPC
What was asked in isro civil interview
please what is the number of bars required for a column of 6mx6m and 450mmx300mm,its a commercial building (Church)