Answer Posted / rajesh.d.v.s.p.
normal design per square meter of slab we take 15kg of steel
hear thay given 100 sq.ft
1sq.ft = 0.0928sqm
100sq.ft=.0928*100=9.2 sq.m
total steel requried = 9.2*15=138 kgs
Is This Answer Correct ? | 8 Yes | 8 No |
Post New Answer View All Answers
what is the maximum number of course that can be laid according to IS code and the max height.
it is possiblee to produce concrete with out cracks...
hii.plz send me hpcl placement papers for officers trainees for graduate engg plz my email id is ajm_knit@yahoo.com
What are segregation and bleeding?
Define What is Civil Engineering?
what will be the cost of thickness of 125mmor rcc measurement of 52x33.75 feet
insted of bentonite we can use any alternate material in piling ?
HOW TO CLACULATE CEMENT AND SAND CONSUMPTION FOR THE STAIRCASE KOTA FLOORING IN THE RATIO OF 1:4 50 MM THICKNESS
What is Architect-Prepared Contract?
WHAT IS THE CAUSES OF RUTTING ON FLEXIBLE PAVEMENT?
How to calculate the area of a irregular sized land in square feet?and what will be the total area of this land South-51.1ft , North-47.7ft , East-53.3ft , West-54ft ?please explain me how to calculate?
strength vs shape factor
what is the list of building construction equipment & teir output?
I am in India. Employer A got approval for my H1. But they have no job for me now. Company B is going to file H1 for me. They do not know about company A. Is there any way that I get approved H1 of company A transferred to Company B?
Explain the term 'Gross unit rate' and identify the items that may be included in the gross unit rate.