In operation modes i have schedule some jobs in off peak
but the jobs are not completed with in time of off peak
what happen at this time whether they wait until jobs
complet or change to peak mode ?
off peak time interval is from 6.0 pm to 6.0 am and
peak time interval is from 6.0 am to 6.0 pm
Answer Posted / m k chaitanya
During operation mode switch the existing processes are continued to complete their jobs and after completion of their jobs they will switch.so here processes are wait until they completed their jobs later they will switch.
| Is This Answer Correct ? | 20 Yes | 0 No |
Post New Answer View All Answers
Why can't we do it thru some other client?
What is the purpose of webdisptcher and Installing and configuring Web Dispatcher what are the prerequisites?
How to identify a particular T_Code has been modified or not? If yes, how to identify who modified particular T_Code in current system?
Explain what is the purpose of tdevc ?
please share sap basis admin interview questions .. thanks sadik
Have you done any up gradations?
Hi ,All What is the multi-threading and max connections for rfc. Actually i am facing problem while send large amount of idocs to external system using middle ware tibco r3 adapter. And how to enable these in SAP ?
How would you troubleshoot the 'system seems slow'?
If you have a long-running Job, how do you analyse?
Explain what is the use of reference and service user in sap?
While doing implementation do you get any issues?
Explain logon groups?
Explain what is the importance of table t000?
How to transfer request which is created directly on quality server & has to be moved to in production server?
suppose in the landscape there is development, quality, pre-production and production system is there. what is the route(transport route) between pre-production to production? and why?