HOW we can calculate the quantity of sand and cement for 1:4
plastering with a thickness of 12 mm..total area need to be
plaster is 985 sqm

Answer Posted / k.l.b.srinivas

ACTUALLY I THINK
1 CUM = 35.315 CFT
12mm = .5"/ .039 feet /.012 M
so. 12 mm thick plastering = 1/ 0.012 = 83.33 Sqm

for 1 Cum cement required is in 1:4
1/4*1440 = 288 Kgs.
so, for 83.33 Sqm we need 288 kgs of cement & 288*4 = 1,152
Kgs. of sand multiply the amount with 985 & divide it by 83.33
3,404 Kgs. of Cement = 68 Bags.

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

If specific gravity of cement is less than 3.15 what is the cause?

1873


Please tell me the quantity of cement, sand, flyash, foaming agent required for 1 cubic meter of cellular lightweight concrete blocks. also , is there any admixtures required for the CLC blocks production.

1962


States some of the commonly used commands in cad software’s?

771


how many mason and labaur work for a 1 brass bricks plz let me know the calculate & how to made calculation for this and whats the formulas for this?

5735


What is the average density of soil?

679






What is the difference between linear dimension and aligned dimension?

636


Can we apply curing compound on ceiling (slab Bottom)

368


how do you stabilize a waterlogged area in road construction

6314


How much is the cover for slab?

740


How do you change a dimension value in solidsworks?

781


how can we calculate steel value, depending on load

1700


material used for mendrel use to bend epoxy coated rebar

1707


What expenses counted in contingencies and how much it is in related to built-up area of the building.

1313


how i convert mm into standard wire guage (SWG)no.

2602


What do we mean by partial moment release ??

3369