725KW Three DG set Synchronised but DG no-1 power showing
750KW DG n0-2 power showing 500KW DG no-03 showing 500KW.
DG is Shynchronised but why this different power showing?
Answer Posted / kj
If the DG's are the same rating then the load sharing is
out of adjustment.
Load sharing can be by speed droop (see answer above) or by
load sharing controller.
Adjustment of either of these can rectify problem.
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
Which motor will you choose which can operate in both lagging as well as leading power factors?
1 “earthing” for bonding of equipment and circuits to common plant earth electrode potential, 2 “protective earthing (PE)” when this bonding is required for personal safety provisions 3 “grounding” for interference suppressing bonding of screens, sys-tems with ground level 4. low-impedance earthing ? 5.primary earthing system and secondary earthing system what is that? 6.earthing electrode or mesh net earthing electrode ? very confusing , simple but very informative help required ? i will be very very thankful to you guys.
best manufacturer for busbar for outdoor switchyard having double bus bar scheme, can any one share technical specification of busbar. 132kv voltage ?
what is the sludge current
Explain the different regions in frequency response?
what is the difference between active power and reactive power and apparant power in practical as well as theoritical
full form of flry b
why on axial hitting up of air blast on hydrogen produced in oil circuit breaker,temperature rises of the core of the arc?
how is working bearing heater?
what is meant by carrier aided trip protection in transmission line
what is excitation/
What is main cause of cable's terminal point burned in Lug on high temperature although lug and cable selection is ok as per stantard and also tightness is ok as per situation. so please take in deep and tell correct answer thanku.
prove that power consumed in 3 phase delta system is 3 times as compared to 3 phase star system
What is meant by earthhing of a magnetic flow meter and when to use empty pipe detection?
Work done in a free expansion process is