how i meggar value of 11kv alternator winding.and with meggar.
Answer Posted / kj
See extract from service manual for HV alternator.
A 5000V motorised megger or similar instrument should be
used. Separate the three neutral leads,
ground V and W leads and megger U to ground. Repeat for V
phase with U and W grounded and W
phase with U and V grounded. Minimum acceptable limits
after 1 minute for each phase are:
New machine 300 M
In-service machine 150 M
The insulation resistance should not be less than specified
and the polarisation index should be in the
order of 2 or greater at 20 ÂșC.
(PI = IR10min / IR1min)
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
what is the minimum clearance between a 11KV 150KVAR capacitor cell and series reactor.can a series reactor can be mounted in the same structure of the capacitor cells structure
Will an earth leakage trip be activated if the component or wiring is faulty on low voltage equipment.Example An electrical Cat Scarer placed in the garden and water gets into the wiring.
how indusrial diesel generator work
What are the necessary components of the feedback control system?
why we get 2 differnet values for power factor in 2 watt meter method in 3 phase
If we use 250A MCCB as a incomer in Control panel for a fault level of 50kA for one second ,assuming temperature rise from 85 Deg. to 100 Deg , Then what will be the Aluminium Bus-bar size for 250A MCCB? Explain in detail.
Benifits of 3ph 4 wire metering over 3ph 3 wire
what are the stresses in circuit breakers ?
sir my exam is on 19/6/2013 under electrical branch pls send me sample aptitude questions as well as sample technical questions for jindal steel and power company
what is the relation between size of the anteena and wavelenghth of radiated wave
The electrical energy required to raise the tempreture of a given amount water is 200 kwh. If the heat losses are 20%, the energy required is?
what is the pre charge circuit,what will be work which function it will be use plz tell me
What is the difference between PS & metering CT (5p20,0.5 etc.)? Why in PS class CT only Vk is given ? Is PS class CT is more accurate than metering CT?
Why the symbol of register is "zig zag"
Block diagram of Power line communication?