how to creat mix m-20? and how to check shuttering & how is
mark layout at open ground
Answer Posted / ratheesh
M20 = 1:1.5:3
shuttering
1. Slab & beam bottom level should be checked.
2. All props and bracing pipes should be checked,
3. Beam & Slab side alignment should be checked
4. side shuttering plump should be checked,
5. All room dimensions & Openings dimensions should be checked
6. before reinforcement should be apply shuttering oil.
Layout
you should be use pythagoras theorem...
Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
How to find beam R/F cutting length
What does civil engineering mean?
How and where are aqueducts built?
How to calculate unit weight of concrete for m40 grade.
how to Concrete cubes testing curing time 7 days casting date 24.05.17 testing date ?
What is the strength of cement?
How do you compute the volume of airflow?
What is the significance of cost estimate knowledge for an architect?
why is M25 and Fe 500 assumed to be most economical? i feel it is not.This is because higher grade of concrete and steel has higher lapping length and anchorage length compared to lower grades..
how much tempareture are required to make liquid state of pid leed
What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?
how to calculate steel for slab or footings?
Please tell me Detail cost of providing& laying nominal mix design 1:2.5:5,40mm nominal size.curing complete e/c cost of form work in foundation and plinth i/c carriage.
How much Tolerance factors like 1. brick work 2.plaster 3.painting 4.floor tiling 5.wall tiling 6.shuttering 7.concreting 8.steel
While calculating the weight of the steel per running meter, the formula used is [(dxd)/162]. Why 162 is used in denominator & how it is derived?