How can u prepare mix design for concrete?
Answer Posted / md murtuza ali
concrete mix are of many types ,generally for domestic construction we use M20 grade of concrete where 'M' is the mix
of ingredients such as cement, agrregates(fine and coarse) and water and '20'refers to compressive strength of concrete for 28 days of curing with water.
steps invovlved in concrete mix are
1)collecting raw materials such as cement (43 grade or 53 grade),fine agrregate(sand)and coarse aggregate(gravel or stone)
2)batching:-weighing of all the raw materials the ratio of M20 grade of concrete should be (1:1.5:3) which means 1 part of cement,one and half part of sand and three parts of gravel with water by water cement ratio.
3)the water cement ratio should be 0.45 of all mix
4)mix the all ingredients such as cement ,affregates and water.
5)after mixing the freshly mixed concrete should be used for its application .the initial setting time of concrete is 30 mins and final setting time sholud be less than 10 hrs.
so this was about the mix design for M20 concrete.
Is This Answer Correct ? | 42 Yes | 8 No |
Post New Answer View All Answers
how many sqft or cft of work done by a mason per day in all works such as brick,block,concrete,shuttering carpenter,reinforcement fabricator,painter,door window carpenter.....everything thank you
What is meant by solid geometry?
For Wet Mix Mecadam design what is Optimum moisture content
What is the effect of a building collapse?
How to activate isometric axes in cad?
How do you compute moisture correction using the parameters gathered from Nuclear Density Gauge Apparatus and the moisture contents results from the lab.?
How do we determine the specific gravity of a cement?
GIVE US DETAIL OF YOUR PRESENT EMPLOYMENT STATUS?
Why we provide hair pin for shed
what could be the production cost of 1 cum of concrete by CP30 plant
WHAT IS THE % OF CONCRETE WASTAGES PERMITED IN A LARGE PROJECT ? AND WHICH IS CODE TO BE REFERED.
If density of cement is 1500 Kg/m3, the how is specific gravity 3.15 ? (Density of water is 1000 Kg/m3)
what is derating factor in cable? what does it mean if derating factor is high/low in terms of thermal resistivity of soil?
Differentiate orthographic and isometric projections?
rimmer in pile foundation