How manu days after the casting of a slab another slab can
be casted above it?
what is the total curing time of a slab if ponding is not
done on it?
Answer Posted / manjunatha.h.s
How many days after the casting of a slab another slab can
be casted above it?
what is the total curing time of a slab if ponding is not
done on it?
As per codal provision 7days curing by ponding +7 days
continues sprinking should be done, Minimum of 14 days
curing should be done to start casting a new slab upon it
therewhich Back propping should be given to the lower slab
in the column capital portions,
In case if ponding is not done, continues water sprinking
should be done for 21 days
Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
What is portland cement
what else we can add rather than admixture in concrete to reduce the cement quantity?
What is the maximum strength of cub compress strength in one cub testing
how to find ssm in foundation?
how to calculate the mortar for 10'*10' size room for both plastering and for masonry work?
how much used soil in 1 brick of standard size?
What is capicity of cap lock scffolding stander(vertical member) and ledger of different size?
Curing time for 1)R.C.C slab 2)B.W 3)Plastering
how to calculate MR 9(derivation)
how to calculate mivan shuttering matrial
what is moment-curvature relationship in semi rigid connections??
what do you mean by yeild stress of a material? What will happen when hit is given to cement?
GIVE US YOUR FULL DETAIL OF THE FOLLOWING… FULL NAME.. PERMENENT MAILING ADDRESS DIRECT CONTACT NO E MAIL ADDRES.
WHERE CAN I GET THE PREVIOUS QUESTION PAPERS OF APGENCO FOR THE THE POST OF Tr.ASSISTANT ENGINEER(CIVIL)
How much quantity of cement and sand required for the inlining of 610mm dia MS pipe 8.7mm thk.Inlining thickness is 10mm and CM ratio is 1:1.5.