I have a 600VA UPS for computer only. It holds for
20minutes only.
1. Can it be upgraded for longer period.?
2. Can it be used for one ceiling fan and a tube light? If
yes, how to upgrade?
Answer Posted / ehsan rabbi
u r telling that it holds for 20 mins. But in practice it
doesnt last more than 4/5 mins. does it ? Actually it
depends. A 600 VA UPS running from a typical 12 volts 7.5Ah
battery can handle 600 x 0.8(pf)x75%(eff)=360 watts of load
only. There are many other facts that im not breaking down
right now.
The fact is simply this. U can prolong your backup time by
adding higher ampere-hour battery like 12 volt 8Ah or
maximum 12 volt 12Ah but not more. If u want more backup
u'll need much higher AH rated battery (like 40Ah) and at
the same time u must upgrade your battery charger to a
higher level otherwise those heavy batteries will take
forever to charge fully /partially or whatever. Bottom line
is u just have to spend more bucks not only for battery but
also the built in circuitry mounted with the UPS.
Both the ceiling fan and tube lights(which includes
ballast)have raw power factors (0.6~0.75) That means an 80
watts fan can consume upto 115 watts of power. To drive
those loads u not only need high amps battery but also high
volt-ampere machine (eg. 1200 VA)
Is This Answer Correct ? | 18 Yes | 2 No |
Post New Answer View All Answers
what is the difference between changer, converter and transformer?
How to determine the breaking capacity such as break down current and break down voltage for VCB and CT's.
Advantage of LT panel vs HT panel
What are PLC leader logic program method
What is Load sharing of Transformer ?
Describe the colour rendering properties of i) tungsten filament lamps ii) tubular fluorescent lamp
Why we use ups battery and dsdb battery in thermal power plant
How are load losses and no-load losses measured at site in a DG set?
in non technical way how can u define POWER FACTOR??
How is the speed of a DC shunt motor related to the armature current?
WHAT IS IM (INDEX OF MOUNTING )IN MOTORS
What are the site acceptance tests for power cables, DG Sets, LT panels & 30kVA UPS ?
what is the correct method for the outdoor termination of 19/33 KV HT cable step by step?
what is the working principle of a DG Set, Alternator, & exiter
Why MCCB is Getting tripped sometimes when there is no load in the Midnight ?