what is the work (job or role)of sap-sd consultant in a
cutover activity???
Answer Posted / shriyasuhaas@gmail.com
Cut over is the activity that happens 2 days before the go
live . During this activity as a sap sd consultant you need
to take care of loading the master data into the sap
legacy system thorugh LSMW or BDC in the form of FTP(File
transfer process) .
The second activity that is needed over here during
cutouver is to sit with Technical team and understand the
interfaces required ; programs to run the interfaces and
their connectivity as thorugh these interfaces only one
will be connecting the non legacy to leagacy and also check
the movment of data is carried sucessfully or not
Is This Answer Correct ? | 5 Yes | 0 No |
Post New Answer View All Answers
How can you tell if a transport entry is in the process of being imported in sap ? : transportation management
Explain about distribution channel?
Define to which organizational element is central in shipping?
Can any one explain how we will configure milestone billing , periodic billing and which scenario we will use?
What is the procedure of Make to order configuration. Plz answer me, Thanks in advance.
Can we assign multi distribution channel to a single customer in sap sd sales process. If yes then how?
What is delivery document?
I have a shopping mall. If a customer comes to my mall and if he purchase or not anything I give him pen free. How we map it in sap?
customer hierarchy in sap sd for account determination
What is product attributes in sap sd?
How to assign sales group to sales sales office?
What is sap posting period?
Are you familiar with the partner profile setup? I am sure when these EDI transactions must have been posted through SAP as idoc?
What’s forward scheduling and backward scheduling activator? There’s a concept called forward scheduling and backward scheduling logic when you do an availability check whenever your order is created system will check whether it’s forward scheduling or backward scheduling, if it’s fatal we have a concept of how is it working, how is that you created as part of your available promise concept? Whatever that date is being considered as part of the logic, whatever the date that is configured or we maintain the data to say know that system tell to create this output back scheduling
Infostructure filling we have two company codes and new infostructure s004 for filling. We must fill it with data from first cc only. Is there any problem if the people who create orders, deliveries, and billing of second cc work at this time?