How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step
Answer Posted / zuber ahmed
Volume of Dry Mortar = 35% of volume of Brickwork
Volume of Mortar required = 0.35 + 1 = 1.35 cu.m.
Cement required = 1/6 X 1.35 = 0.225 cu.m. =6.8Bags
Sand required = 5/6 X 1.35 = 1.125 cu.m.
Bricks required = 500 Nos.
Is This Answer Correct ? | 10 Yes | 43 No |
Post New Answer View All Answers
How to produce the Concrete Grade 30mpa at 12hour? How to prevent for plastic shrinkage crack? How can we produce fire resistant concrete?
What is the distance between railway tracks?
how to identify the failure of building by expansive soils
What is different between DI Pipe and CI pipe?
IS STEEL BARS IS AS PER ISI TRANSVERSE RIBS SHOULD BE UNIFORM IN DISTANCE, PLEASE EXPLAIN WHY,
What are the advantages of building a dam on the river nile?
Define What does civil status mean?
how much st. steel is required for staging of concourse slab of a elevated metro station allowing through traffic .
What is thumb rule in quantity and cost estimation of a residential building?
How to find coloumn vertical cut length floor to floor & lap + bend or anything plz clearfiy
Why reinforcement done in shorter span in two way slabs
How to plan a project
i need the syllabus for the direcr recruitement of executive engineers in andhrapradesh
What is the method of soil replacement test?
What is quantity of cement and sand required for 2000sqft of tiling?