I heard Thump rule about beam depth is 1" per 1' length. Is
this correct? If not please tell me the thump rule.Thanks.
Answer Posted / amreeta
no it is to calculated like
100mm depth per 1m span ..when the total depth(D) is not
given.
after you get the total depth(D)
then calculate effective depth(d)
d = D-(cover of the beam +radii of the rod)
assume cover = 20-25mm
dia of the rod 16-20mm
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
how much of the strength comes from post-production curing
Labor requirement for each item needed? Lean Concrete 103.550m3 Concrete for Foundation and Structure 1753.000m3 Expansion joint 288.000m Contraction joint 127.000m Dowel bar 450.000m
Why are the bolts that hold steel rails together in oval holes?
One plate (women civil worker lifting Plate - Satti) sand measures how many cubic feet?
How to compute minimum number of columns required for a site from area of site?
why we use 19x9x9and 20x10x10 but not other
What are the problems one might face while having a Cantilever balcony?
A rock anchor 3 1/2” in diameter is placed in rock. The which has an allowable shear strength of 1200 psi. Determine the required anchorage length to safely carry a 80 ton load using a 2.0:1 F.S
Explain what is the release of lien?
though u r a civil engineer, y r u interested in tcs???
Draw the cross section of a boundary wall and label its part with detailing?
What do you mean by the word 'shear'?
what is the difference between np2 and np3 concrete mix
what is the meaning of degreasing of the euipment or line.
Mention what are the composition of a landfill?