I heard Thump rule about beam depth is 1" per 1' length. Is
this correct? If not please tell me the thump rule.Thanks.
Answer Posted / amreeta
no it is to calculated like
100mm depth per 1m span ..when the total depth(D) is not
given.
after you get the total depth(D)
then calculate effective depth(d)
d = D-(cover of the beam +radii of the rod)
assume cover = 20-25mm
dia of the rod 16-20mm
Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
What is the cost difference between site mix and ready mix concrete per cubic meter
what is diversion?
Why are pull-out tests performed for soil nails?
What is demising walls?
what is high type road and low type roads
What is kn measurement?
What is the procedure of concealed plumbing in toilets?
how i convert mm into standard wire guage (SWG)no.
What is the standard volume of pharma in cub ft
Required amount of Steel bars, cement/ square feet for roofing of residential building upto 3rd floor.
length where bent up is made in slab of bridge from one end
We are into industrial flooring (epoxy flooring) business. We buy material from manufacturers.We supply and laying the to companies. In our billing what tax/ taxes to be claimed from companies? Are we applicable for only WCT or any else?
I need Bhel engineertrainy test papers in civil engineering please send to email id - hisandy66@gmail.com
I am a civil engineer . I am also selected for sbi clerk interview which is to be held on 4th May2010 is there anybody resembling the same? what question can be asked and what should be the probable answers?
detailed calculation of the amount of cement used?