If the maximum demand is 120 KVA in a building, then what is
the Current taken according to load given ? Formula for it ?
Answer Posted / jose
120 kva means you have to supply 3 phase load.
3 phase load with 415 v and unity pf can take a current
according to eqn kva=1.732*Kv*I
I=120*1000/(415*1)=290 A appr
Is This Answer Correct ? | 6 Yes | 0 No |
Post New Answer View All Answers
does buccholz in a transformer use batteries
any idea abt REVERSE METERING concept.........?
what is the pulse and audio frequency transformer? what is different between induction regulators and tap changing transformer?
what is the difference between elcb and rccb ?
DERIVE AN EXPREION FOR MAXIMUM POER TRANSMISSION, WHAT ARE ITS APPLICATIONS.
What are the advantages of hydropower?
he compression ratio for a petrol engine generally lies between
Why we use duplex coil and hook switch in telephone system?
Explain about c.t?
how can I calculate charging current of cable/overhead conductor? what is roll of voltage in it ?
a simple c++ program to calculate simple interst with its data members as private
May I know how much values to be set for earth fault, over current and short circuit values at 11kv side? I have 11kv van 1250amps rating. Present it's taking load 80amps?
how we calculate the withstansing current capacity of wires&cables?
Which of the following alternatives will be cheaper (1) A 100 h.p AC, 3-phase motor (2) Four motors of 25 h.p each (3) Five motors of 20 h.p each (4) 10 motors of 10 h.p each explain
what is the differencce inn series and cascade connection??