I'm puting roof slab M20 Design Concrete,Twoway slab how
many days wait for remooving of shuttering?

Answer Posted / s.prabhu

as per IS456 Centering deshuttering period is depends upon
the span of the beam / slab.

Span less than or equal to 3m is 14days

Span more than 3m is 21 days.



Regads
S.PRabhu
9901702081

Is This Answer Correct ?    2 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Name the main components of a cad gui?

1038


can you please tell me what the current rate of construction material and different construction labourers charge in bangalore ???

1446


TO CONSTRUCT A 1800 SQFT CAPACITY UNDERGROUND WATER TANK HOW MUCH CUFT CONCRETE IS REQUIRED AND HOW MUCH REINFORCEMENT IS REQUIRED. FOR COSTING

2099


What is the diff between cad & cadd?

651


What are the responsibilities of a site manager?

624






cud any one send me tech quest paper(civil engg) at tarizus@yahoo.com

1743


what are the Task work of different labour.?

2162


In which code the the maximum height of concrete casting has been explained

2332


How to compute minimum number of columns required for a site from area of site?

1535


Please tell me any one, how many quantity concrete paver block fixing perday ( 8hours) per mason??

1170


how many BSCs can i connect to the HUAWEI MSC

1836


Who designed the city of washington dc?

682


can you provide a link for manual design of building?

1122


I have to design brick column and footing (note: without any reinforcement). Can somebody post me the design or suggest a book where i could possibly find the design? Plz help very urgent

1782


How to calculate chejja reinforcement

1898