what is steel consumption for high rise building column,
beam, slab,footing
Answer Posted / s.k.roy
Based on experience the Consuption for a Building of 10-15
Storey :
Beams 125-140 Kg per cu.m of Concrete
Slabs 80-100 Kg per cu.m of Concrete
Columns 350-400 kg per cu.m of concrete
Footings100-125 Kg per cu.m
In general for a Eartquake Resistant Str in Zone 3/4 the
steel consumption can vary between 6.5 to 7.5 Kg per
sq.feet of Constructed area
Is This Answer Correct ? | 29 Yes | 7 No |
Post New Answer View All Answers
What is the name of this multiplication factors ?
what is the formula to find the diagonal shape stirrups?
What is the difference in painting using Roller and Brush? What is the paint consumption difference? As per IS one coat of painting is painting from left to right and top to bottom whether this can be done using roller ( Roller Stick height and feasibility) ?
how can we calculate steel value, depending on load
what course did you consider thinking before you enrolled in college?
Material calculation of cm 1:6 for 1sqm
please what is the number of bars required for a column of 6mx6m and 450mmx300mm,its a commercial building (Church)
resins are not soluble in water soluble in spirit used in varnish left behind on evoporation of oil
How many axes do cartesian coordinate system has?
Who name us Engineer & Why?
What is oneside mat. And explain
what is the difference between prime coat and tack coat in road construction
What is the difference between Grade I, II and III of GSB?
How did the romans get water up hills using aqua ducts?
can we use PPC for concrete wall, If yes, what is the concrete (PPC & OPC) grade for Non- load bearing concrete wall, load bearing concrete wall & for cellar retaining wall.