How do we calculate the building footing calculation ?

Answer Posted / guest




Dear friends generally we do this footing calculation like
this two method =
(A)1st method =i)1.500 m x 1.500 m x 0.500 m = 1.13 Cum.
ii)½ x ( 1.500 m + 0.250 m ) x 1.500 m x 0.200 m = 0.260
Cum. (B)2nd Method =i)(1.500 x 1.500 x 0.200)+ (0.250 x
0.250 x.0.250)= 0.460 Cum.
ii) ( 1.500 x 1.500)+ ( 0.250 x 0.250)/2 x 0.200 = 0.231
Cum.
( But I think it is not proper procedure so please you do
properly )

Is This Answer Correct ?    10 Yes 33 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How much percentage of brick bats allowed in CD-75 bricks

1889


What are the types of slump?

642


How to make a c++ program that converts any base to base 10?

1625


What is the worlds largest concrete dam?

717


crank types

1885






I am in India. Employer A got approval for my H1. But they have no job for me now. Company B is going to file H1 for me. They do not know about company A. Is there any way that I get approved H1 of company A transferred to Company B?

1674


Draw the cross section of a boundary wall and label its part with detailing?

4152


what is the composition of good brick ?

1471


How is calculate the cube molt

1795


what is the water cement ratio of 1:6 and 1:4 cement sand mortar. reply soon

2343


how many spacers we need for 1 ton reinforcement? aprox.

4918


how to convert cement, sand aggregate quantity from M3 to kg with full description?

1596


residential projects,structural.

2415


For sloping slabs or sloping beams why the tension steel from either side of ridge is taken into compression zone of other side?

1637


what is the most suitable foundation when construct a bird watching tower in a marshy land

1427