9*9 1:4:8 ratio using for p cc work please tell quantity
40mm aggregate ,sand &cement

Answer Posted / manikandan ramia sankaran

1. 9.00m x 9.00m x .15m
= 12.15 m3

12.15/(1+4+8)[x] 1.56 = 1.458m3 of cement
sand = 4 x 1.458 = 5.832 m3 of sand
4omm agg = 8 x 1.458 = 11.664 m3

Is This Answer Correct ?    7 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

how to calculate the density for high density concrete ? or is it same as the density of RC?

1880


Why should you consider yourself fit to be hired by jindal steel.

3929


What is the software used in civil engineering?

661


How to improve the strength of fly ash bricks to avoid corner damge? How to get the color lighter similar to normal concrete blocks/

1360


why we are useing plastic under the lean concrete?and whts the advantage?

2161






How to calculate steel for beam slab and column

1367


for pretensioning which will yield first and same for post tensioning?

1715


Give list of building construction equipment & explain about them in brief. How much is output of JCB, POCLAIN, Steel cutting & bending machine, material hoist, tower crane?

2596


HOw much % of premium on DSR-2013 currently

1542


How much sand and cement requirement for 1 SQM 125mm thickness Brickwork

459


I want to know the material required per square foot in rcc roof. i.e. steel: kg/foot, cement/foot etc.

1523


What is Grid floor and mention its advantages ?

2761


the volume of cement req for 70cum of brickwork in 1:6 cement mortar is approx is equal to 3cum 5cum 7cum 1ocum

1631


punj loyed and sapurjl palanjl

1885


in one SQM plaster how much Cement and sand consumed in ratio 1:4

1673