How du we calculate dry cement (in Bags) for any concrete,
also sand and aggregate? How many bags of cement does 100
cft of concrete 1:2:4 require? Procedure to calculate the
required amount. Also if there is any easy thumb rule to
find out.
Answer Posted / dushyant bansal
Esasiest way to calculate the cement content is thumbrule
as if in 1:2:4 concrete there are 8 bags of cement per cum.
of concrete i.e. 35.325 cft concrete 8 bags cemnt
In schedule of rates amount of cement, sand and aggregates
according to their ratios is given.
Is This Answer Correct ? | 10 Yes | 3 No |
Post New Answer View All Answers
1)Why we can use half brick in 4inch wall and 2)why not in 9+inch brick wall
How much of the strength of concrete comes from post- production curing?
one steel fixers how much ton steel fabrication he will do same how much tone he will binding?
what is parametre for M25 after 7 days strength
RR masonry rate analysis
While doing civil foundation of machinery. How will you process for it? & We also fixing plates at top surface of foundation, then what is the procedure?
what is differences between ferrock and concrete ?
Consumption of Binding wire for fixing of cover block in vertical surface
for a column of size 400*230mm column reinforcement= 8-20x(cant write the symbol,i hope u guys undersstand,something like (fi) column stirups=8x@(4l) 230c/c 1)what does these mean 2)how to calculate quantity of steel for this column(ceiling height 11 ft)
Define unit atmospheric pressure? Difference between gauge pressure, absolute pressure?
step by step procedure to find out the percentage of steel in coloum,beam,slab,footing in detailed
why the profile of shell of natural draught cooling tower is hyperabolic.
How is improve my knowledge in construction industries....
For elevated service Reservoirs what will be the output of each skilled carpenter and bar bender.
What is meaning of FREE STANDING STAIRCASE ?