Suppose you did all your work in a 32 bit system, the
production server is 64 bit system, you find that during
UAT, the system fails and is not working, how will u
communicate to your customer, what solution will you
provide to the client?

Answer Posted / shri

having 1 round of testing on 64 bit environment

Is This Answer Correct ?    0 Yes 4 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Your hardware vendor left you voicemail saying that a snowstorm in the Midwest will prevent your equipment from arriving on time. You identified a risk response for this risk and have arranged for a local company to lease you the needed equipment until yours arrives. This is an example of which risk response strategy? A. Transference B. Acceptance C. Mitigation D. Avoidance

770


Which of the following is true regarding NPV? A. NPV assumes reinvestment at the cost of capital. B. NPV decisions should be made based on the highest value for all of the selections. C. NPV assumes reinvestment at the prevailing rate. D.NPV assumes reinvestment at the NPV rate.

557


This measurement is the value of the work that's been completed to date: A. PV B. AC C. EV D. EAC

644


You are a project manager working in a foreign country. You observe that some of your project team members are having a difficult time adjusting to the new culture. You provided them training on cultural differences and the customs of this country before arriving, but they still seem uncomfortable and disoriented. Which of the following is true? A. This is the result of working with teams of people from two different countries. B. This condition is known as culture shock. C. This is the result of jet lag and travel fatigue. D. This condition is known as global culturalism.

687


All of the following are true regarding the WBS except: A. It is a deliverables-oriented grouping of project deliverables and elements. B. It defines and organizes the work of the project in a hierarchical form. C. It provides a framework for the work of the project, and work not shown on the WBS is not included in the project. D. It defines all the deliverables of the project, but the activities level should not be listed on the WBS.

752






You are a project manager for Bluebird Technologies. Bluebird writes custom billing applications for several industries. A scope change has been requested. You know change is concerned with all of the following except: A. Managing change B. Verifying change C. Influencing causes of change D. Determining that a change occurred

513


You are preparing a cash flow analysis for a project the company is considering undertaking. The project's cost is $525,000, and expected cash inflows are $125,000 the first year and then $75,000 per quarter the second year and $100,000 per quarter after that. What is the payback period? A. 16 months B. 27 months C. 32 months D. 28 months

629


You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the company. Your lead engineer has given you the following estimates for a critical path activity: 60 days most likely, 72 days pessimistic, 48 days optimistic. What is the expected value, or weighted average? A. 54 B. 66 C. 60 D. 30

710


You have been assigned to a project in which the objectives are to direct customer calls to an Interactive Voice Response system before being connected to a live agent. You are in charge of the media communications for this project. You report lo the project manager in charge of this project and the VP of marketing, who share responsibility for this project. Which organizational structure do you work in? A. Functional organization B. Weak matrix organization C. Projectized organization D. Balanced matrix organization

725


You do not expect the types of variances that have occurred on the project to date to continue. If BAC = 300, ETC = 275, PV= 300, AC = 200, EV = 250, and CPI = 1.25, what is the EAC? A. 240 B. 250 C. 475 D. 150

565


All of the following are true regarding the tools and techniques of Activity Sequencing except: A. GERT uses analogous methods. B. GERT allows for loops. C. GERT is a conditional diagramming method. D. GERT allows for conditional branches.

621


You are the project manager for Lucky Stars nightclubs. They specialize in live country and western band performances. Your newest project is in the Planning process. You've published the scope statement and scope management plan. The document that describes who will receive copies of this information as well as future project information, how it should be distributed, and how the information should be stored and filed is which of the following? A. Scope management plan B. Communications management plan C. Information distribution plan D. Project charter

606


Explain the Principals of Management

598


You work for a large manufacturing plant. You're in the Initiation process of a new project for an overseas product release. This is the company's first experience in the overseas market, and they hope to make a big splash with the introduction of this product. The project entails producing your product in a concentrated formula and packaging it in smaller containers than the U.S. product uses. A new machine is needed in order to mix the first set of ingredients in the concentrated formula. Which of the following actions should the project manager take? A. The project manager should document the project's goals and known deliverables in a high-level overview document and recommend the project proceed. B. The project manager should document the project's goals and known deliverables in a high-level overview document and assume the project is a go. C. The project manager should document the project's goals and known deliverables in a high-level overview document and recommend a feasibility study be performed. D. The project manager should document the project's goals and known deliverables in a high-level overview document and deliver it to the stakeholders.

763


Explain on the project management life cycle process?

476