9*9 1:4:8 ratio using for p cc work please tell quantity
40mm aggregate ,sand &cement

Answer Posted / bala

1. Consider 9.000m*9.000m*0.150m
Volume - 12.15Cu.m

* Cement - 41.31 Bags
* Sand - 6.075 Cu.m
* c.agg - 12.15 Cu.m

Is This Answer Correct ?    4 Yes 5 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what"s the sort of beams?

1819


What is the ideal size of the living room ranges from small to large size?

664


which software is better for design and analysis of buildings (stadd pro ) or (Etabs)

1836


what is differences between ferrock and concrete ?

1428


1) What is meant by C-soil in geotechnical Engineering? 2) What is Eve board? 3) What will happen when heat is applied to cement? 4) what do you understand by the lateral dimention ?

6113






How to testing voids of filled aggregate in bitumen mix design

1464


can we compare the combined core of DBM and BC density with average density of Lab DBM and Lab BC density

1700


Providing and casting in situ cement concrete M-25 of trap/granite/quartzite/gneiss metal for rcc, Providing formwork,Curing the concrete and Complete. what is rate per Cum. and what is rate for M-30 Grade Concrete.

2771


What is an ice dam sock?

707


Will going from a 3-tap to 6-tap increase water pressure?

650


what is a well

1506


what is called Bulk Density of aggregate?

1444


que.is ideal size of bricnk use in india,joint size of mortar in massinary ,how many bricks used in 1cum.how to test at site.what is the possition of marka used in bricks?

2029


What black man invented the clothes dryer?

684


Define What are the materials used in building a gravity dam?

737