Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how to calculate the required qantities of cement, Sand and
aggrigate to prepare 1 Cum of concrete mix 1:2:4

Answer Posted / pritesh .c . bhoi

mix desighn = 1:2:4= 7
quantity is 1 cum add 52% westage and shreankage
so 152 cum
cement = 1*1.52/(7)=0.21714 cum (dry volume)
volume of one bag is 0.0347 cum
so no of bags are 0.21714/0.0347= 6.25 nos say7 numbers
bags are required
sand = 2*1.52/(7)=0.43428 cum
course aggregates = 4*1.52/(7)=0.86857 cum so conclution
is
cement =7 nos bags
sand =0.43428 cum
course aggregates =0.86857 cum
if any mistake please informed . thank you

Is This Answer Correct ?    24 Yes 9 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

why we use 19x9x9and 20x10x10 but not other

2170


how to check and keep control on the wastage of material at site

2406


How to find weight of steel in kg if we know the area which is in m2? Following details are known to us, Area=125m² thk of slab=250mm Steel details:T12@200 PS:considering mesh top and bottom with X and Y direction

3102


Minimum and maximum size of the building components

2246


sir how can we find the cement and sand required for making 4" drop

2176


I measured pcc work as 15.34 m cube , the ratio is 1:5:10 ,want to know the cement, sand and metal used for pcc measured as 15.34 m cube at this ratio.

2582


what are the code used for residental building?

2552


What is the absolute pressure scale?

1180


hi guys what happens if you are absent for a supplymentry exam?

1848


What happens to Load at yielding ?

1429


if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.

2143


How to calculate the quantity of ingredients of M20 grade concrete?

2003


what is moment-curvature relationship in semi rigid connections??

2143


What are the different approaches in designing the floors of the service reservoirs?

1193


What is absolute coordinates?

1127