when a primary current injection test is required, it is
accomplished by what?

Answer Posted / brijesh

Primary current injection test require at the time of
commissioning to the current transformer.

The purpose of it is to check the ratio of C.T.

and for checking of C.T. circuit.

The test is conduct by means of primary injection test set.
In test set there is a current transformer and variac.

Is This Answer Correct ?    2 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

WHAT IS IEC? & WHAT IS BENEFIT TO PRODUCT FROM IEC?

1683


What is an ac motor?

687


tell me about roaster switch .& what is the function in transmission & distribution?

2172


What will happen if we on 200kvr capacitor bank(11kv in bus)If there is low load on transformer (1.5 mva 33/11 kv)

1126


how to decide the capacity of accl

1917






what is maxemo work permit procedure

1690


What is the polarization index value ? (Pi value)and simple definition of polarization index ?

764


Why are cables rated for 40 KA for 0.25 Sec fault current rating?

1522


Why saturation region slowly shifted in the left side?

1459


Why phase sequence must be same in any ht motor or generator circuit?if phase sequence doesn't same whatever will be affect on circuit?

1725


bitumar

1808


How LT megger works ?

1697


What type interview questions ask in Electrical technicians

1265


I need HT sphere gap calibration table. Can any body help me.

1529


Mention the disadvantages of low power factor? How can it be improved?

683