when a primary current injection test is required, it is
accomplished by what?
Answer Posted / brijesh
Primary current injection test require at the time of
commissioning to the current transformer.
The purpose of it is to check the ratio of C.T.
and for checking of C.T. circuit.
The test is conduct by means of primary injection test set.
In test set there is a current transformer and variac.
Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
WHAT IS IEC? & WHAT IS BENEFIT TO PRODUCT FROM IEC?
What is an ac motor?
tell me about roaster switch .& what is the function in transmission & distribution?
What will happen if we on 200kvr capacitor bank(11kv in bus)If there is low load on transformer (1.5 mva 33/11 kv)
how to decide the capacity of accl
what is maxemo work permit procedure
What is the polarization index value ? (Pi value)and simple definition of polarization index ?
Why are cables rated for 40 KA for 0.25 Sec fault current rating?
Why saturation region slowly shifted in the left side?
Why phase sequence must be same in any ht motor or generator circuit?if phase sequence doesn't same whatever will be affect on circuit?
bitumar
How LT megger works ?
What type interview questions ask in Electrical technicians
I need HT sphere gap calibration table. Can any body help me.
Mention the disadvantages of low power factor? How can it be improved?