9*9 1:4:8 ratio using for p cc work please tell quantity
40mm aggregate ,sand &cement

Answer Posted / n.lakshmanan

9*9*.100=8.1m3
cement-26.244Bags
sand-67.29cft
40mm aggregate-134.58cft

Is This Answer Correct ?    0 Yes 6 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

can u plz send me ntpc placement papers(civil engineering) at mohit_verma21@yahoo.com

2059


In reclamation works what are the importance of geotextiles and sand?

699


What is the different type of slump test indications?

670


Which tests are performed on soil to decide the type of foundation to be provided.

1640


indian standard split spoon sampler

1556






Consumption of Binding wire for fixing of cover block in vertical surface

1047


what is castigliano theaorem

1835


what is the effect of duration of earth quake on framed structures ?

1805


List out some of the checking’s, done at the completion of construction?

705


What is rate of concrete surface rendering work per sqm

1436


VAT and CST ? Which benefits for buyer ? Why benefits?

1401


residential projects,structural.

2413


How do you calculate reinforcement weight of steel?

670


1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.

1689


what is mc arther pile?

1777