Suppose You are a Test Lead in your company. The dead line
of project is next week.But the product have only 50
percent defect free.How you handle this situation?

Answer Posted / nidhi

In this scenario, Prioritize the defects based on the
impacted functionalities and Severity. Try to get fixes of
such defects and retest them.

For all the Medium and Low priority defects, identify
workarounds if applicable. Also, determine the risk and
impact of the opened defects to the project.

Be ready to document and present this data to your project
management group and the project stakeholders before the
product goes live.

Is This Answer Correct ?    2 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what are the possible test cases for online jobs search portal..if its a job seeker module and any 1 if u had worked on this proj pls share the bugs with sev and priority pls frends i need replies for these queries ..thanks in advance

7139


Hi, this is not a tech question, i have 4 yrs of experience in Mainframe systems, presently as a mainframe tester in pune, i just want to step towards south locatios(preferable hyd), suggest me the best way to get calls from hyd.

1650


Can you explain the elementary process?

653


You may be overqualified for this position we have to offer

1733


What is Test Design ?( Urgent) and Test Design for Printer?

1563






Define what is a critical bug.

672


How to test a Falsh player scrollings?

1763


explain fish model in detail?

1735


You may undergone many projects. Do all the projects match up with customer’s expectations?

708


What are the challenges you faced in your project (Testing) and in your company?

2599


1.Acceptance testing involves procedures for identifying acceptance criteria for interim life cycle products and for accepting them.is that? 2.Acceptance testing occurs only at the end point of the development process; it should be an ongoing activity that test both interim and final products.is it?

1864


Hi, This is vkram.I had completed my B.E in May 2005 & currently i am undergoing Testing Course. I want to join as a Fresher in any MNC. What should I tell why u r coming to testing field & what u did this 2 years?

1524


What is the difference between authentication and authorization in web testing?

716


What is the difference between web based application and client server application?

5464


Hi Can any one tell wht type of questions will be asked in project manager round...urgent plz...

1580