Answer Posted / girish pawar
The question is whats the Basics? and everybody saying about Basic data.
The basics of PP include:
1)Demand management- Planning strategies, PIR, CR .
2) MRP- technical processes of MRP as Net Requmt. Calculation ,Lot sizing , Scheduling , procurement types,then Evaluation of MRP
3)Basic Data management for Planning--- BOM, Routing , Workcenter , material master ..
4) Order management: Production Order, or Planned order, Process order, ot Run Schedule quantities in case of REM.
5) and the necessary activities as Goods Receipt, GI, n the ,backflush to maintain the lifecycle of Order.
Is This Answer Correct ? | 11 Yes | 0 No |
Post New Answer View All Answers
What is routing in sap pp?
What is scope of planning?
What is group bom?
What are basic dates?
What is MRP procedure
Can anybody explain to me why the work scheduling view is required for semi-finished and finished products?
In lsmw which is most important step?
what does SAP business workflow do?
What is pi sheet
Explain LTP.
What is the difference between stock transport order and stock transfer order?
How did you configure the payscale structure?
What is the recruitment cycle?
Mention what are the types of master views for production and planning?
Describe the process for creating and adding to material BOMs. Include release procedure/status, notifications, responsibilities, authorizations, involved systems, Engineering Change Management, and so on.