when a primary current injection test is required, it is
accomplished by what?
Answer Posted / mohammad farman khan-abu dhabi
Primary current injection test require at time of
commissioning to distrubution switchgear.High pot theory.
Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
in my industry we are using 3 step up transformers for induction heaters..i.e 415/580v and other are 11/440v.in power consumption does a step trnsformer makes any difference compared to step up?? plz explain
how does ELR works? explain
What is difference is of VSD,VFD,VSDS, are they the same as the direct current to control dc using above mention
Why the arms of delta in a delta-wye power transmission system are kept constant??
what is rating boiler
describe the constructional features of an auto transformer and its principle operation
Ratings of power transformer,Distribution transformer.
What is resolution of a measurement?
What is core CT & it's function?
define as synchronous generator
bsec exam syllabus (mis)
what is two point starter?
hi, in the event earth grounding is not available in a project, is there any other way to make the elcb work? fyi, i have an instant water heater (6.5kw) installed, however if there is grounding in the heating element inside the heater assembly, i will get grounded. thank you in advance to those who will answer my question.
area control error
what is meant by vector group of a transformer? How can it be derived?