I have 500A load (WHICH IS SEPARATE MDP PANEL),an MCC panel
with 4000A Breaker.Already I have 2500A load.Can I connect
this load directly to the Busbar since I have PROTECTION IN
MY MDP Panel ?
Answer Posted / virendra joshi
Dear friend.
Mathamatically it looks possible but bofore making this
arrangment the other factor which you need to consider.
1. The Rating of a transformer.
2. the Ir seeting of a Breaker.
3. Total contract demand if you are using local electricity
board power.
4. change in OT & WT setting.
by checking all the above peramiters you can go ahead.
Is This Answer Correct ? | 0 Yes | 1 No |
Post New Answer View All Answers
11kV capacitor bank of rating 2.4KVAR, is charged with protective relays of only over current & Earth fault &.......without Over Voltage, Under Voltage & Neutral Displacement Relay. Is it advisable??
give me atleast four differences between circuit and network
why we have and use 3 phase not 2 or 4 or other in power system?
Stator of 3-phase IM has 3 slots per pole per phase. If supply frequency is 50 Hz, calculate the speed of rotating stator flux A 1000 rpm B 500 rpm C 1500 rpm D 1440 rpm
how we can calculate chiller required ampear?
with 3 phase board on a 63 amp rcd is it ok to have 6 electrical showers 2 on each phase and what problems could happen
Define conversion efficiency of a power amplifier.
How servo stabilizer works.
What are the limitations of Kirchoff's laws?
What tests should i carry over on a newly rewinded DC Generator with voltage rating of 38 volts and current rating of 350 amps, to certify that the machine is OK?
Define average demand?
Explain the operation carried out in thermal power stations?
I need the list of Universities who have summer intake for BS degree in Electrical Engineering.?
what is rocking arrangement in arc heating
What is touch potential and step potential?