How to calculate concrete,s cement, sand, metal on the
bases of its ratio. For any volume of work please give me
brief calculation
Answer Posted / raghuram
if 1:2:4 is the ratio the cement require = (1/(4+2+1))x 1440
9density of cememnt)
sand required = (2/(4+2+1))x density of sand
similarly for agg
Is This Answer Correct ? | 16 Yes | 8 No |
Post New Answer View All Answers
How much 1 cum of M15, M20 & M25 concrete weigh?
can i get hindi version of is codes based on civil engineering?
What is the maximum strength of cub compress strength in one cub testing
The foundations are placed below ground level, to increase?
For elevated service Reservoirs what will be the output of each skilled carpenter and bar bender.
Why reinforcement done in shorter span in two way slabs
rate analysis for cement pointing 1:4 , for 100 sq m
Can anyone tell me the sequence of the activities in a drawing room, kitchen & Toilet including civil work, finishing, electrical & plumbing fittings
How to calculate the cement consumption in RR Masonry in CM 1:8 for the foundation of Ground Level Reservoir
What are the advantages and disadvantages of lead products in construction?
CAN WORK WELL UNDER DEAD LINES OR PRESSURE?
Which percentage of carpet area use in plot area of office building.
How to marking the building
Draw the cross section of a boundary wall and label its part with detailing?
What is the requirement for over all CG of DG from the foundation surface to absorb the vibration of heavy set.