How to calculate concrete,s cement, sand, metal on the
bases of its ratio. For any volume of work please give me
brief calculation

Answer Posted / raghuram

if 1:2:4 is the ratio the cement require = (1/(4+2+1))x 1440

9density of cememnt)

sand required = (2/(4+2+1))x density of sand
similarly for agg

Is This Answer Correct ?    16 Yes 8 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How much 1 cum of M15, M20 & M25 concrete weigh?

698


can i get hindi version of is codes based on civil engineering?

3886


What is the maximum strength of cub compress strength in one cub testing

1386


The foundations are placed below ground level, to increase?

790


For elevated service Reservoirs what will be the output of each skilled carpenter and bar bender.

1594






Why reinforcement done in shorter span in two way slabs

1374


rate analysis for cement pointing 1:4 , for 100 sq m

3704


Can anyone tell me the sequence of the activities in a drawing room, kitchen & Toilet including civil work, finishing, electrical & plumbing fittings

1649


How to calculate the cement consumption in RR Masonry in CM 1:8 for the foundation of Ground Level Reservoir

1041


What are the advantages and disadvantages of lead products in construction?

744


CAN WORK WELL UNDER DEAD LINES OR PRESSURE?

1499


Which percentage of carpet area use in plot area of office building.

1395


How to marking the building

1500


Draw the cross section of a boundary wall and label its part with detailing?

4152


What is the requirement for over all CG of DG from the foundation surface to absorb the vibration of heavy set.

1662