Kindly furnish the relation between 7 days strength & 28
days compressive strength of Cement Concrete cubes. Can you
clarify whether the relation gets altered due to various
WATER-CEMENT ratios and type of cements?
Answer Posted / ramir v. agustin
In concrete testing samples aged in seven days should yield
70 percent of the specified strengt requirment and 28 days
sample should yield 100 percent of the compressive strength
required.Water cement ratio and amount of cement plays a
very important role in the production of good concrete.The
stregth of concrete depends on its water cement ratio
Is This Answer Correct ? | 5 Yes | 0 No |
Post New Answer View All Answers
What is change order request?
How much quantity of cement Bag for block masonry (1:4) for 1 cu.m? Block size (150x200x400) Mortar Thickness 20mm
How much cement and sand are required for 1 square feet of plaster at a thickness of 15 mm at a ratio of 1:4?
HOw much % of premium on DSR-2013 currently
to minimize budget cost of building , what can i do
In an aggregate blending plant, water is sprayed before blending is performed. If the fine content in aggregate is as high as 25 %, will not the fines form into lumps / balls and distribution will not be uniform ? Further, the fines will stick onto the interior of pug mill and its content will be low. The mixed material is stockpiled for weeks / months before use. Will it not be better that blending is done in dry condition, and water will be added only during compaction at site. Please forward your comments and suggestions.
I need to do a Compressive Strength Test for a specimen made of Rubber. Before doing the Test on the Machine, I need to have an idea of the Minimum and Maximum Compressive Strength or Yield Strength of the specimen. How can I calculate that?
I just got a first job in Maharashtra and m a fresher. My task is estimate the cost of excavation of earth with J.C.B. can anyone tell me how to do this??
which software is better for design and analysis of buildings (stadd pro ) or (Etabs)
What is dead load impact load live load
how to check and keep control on the wastage of material at site
WHAT IS THE CAUSES OF RUTTING ON FLEXIBLE PAVEMENT?
Caching, Multithreading and RAMBUS are 3 methods for resolving the Bottleneck problem. Please give an explanation for each one (how are they resolve the problem?)
. Write a C program to perform following functions:- a. Declare one integer variable of all the storage classes. b. Print all the variables without assigning any values in tabular format. a. The tabular format must contain the variable name, type, storage class and printed value on the screen in RED color.
What you understand by building codes?