Based on the application size, client requirements etc we
have to estimate the staff requirements...
Assume that application has 5 modules which requires 5
testers to complete the testing with in 2 months.
but client demands that testing should be completed with in
one month then the number of resources should be doubled
i.e. 10 resources should be added to the project to
complete the assigned task.
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
how to connect your project in database?
How do you define a testing policy?
What is regression testing? When to apply it?
How quickly we need to fix the bug? Or how soon the bug should get fixed?
What is the difference between action & script ?
What is the procedure of manual testing?
what risks do u faced u r projest how do you solve
Is quality control similar to quality assurance?
what are the test bugs
What is big bang approach?
Tell me example for Risk,Mitigation,Assumption?
How do u prepare test environment for ur application?
Why is it impossible to test a program completely?
What is PBX Testing & What is Test coverage?
why testcases are written and what is the importance?