Answer Posted / cheekati
MRP TYPE:
A key that controls the mrp procedure(mrp,re-order point,forecast based,time phased planing)used for planning a material.
Lot sizing:
A procedure in material requirement planning used to calculate orders and production quantities.
there are three groups of procedures exist for calculating the lot size.
1. static lot sizing
2. period lot sizing
3. optimizing lot sizing
Is This Answer Correct ? | 13 Yes | 6 No |
Post New Answer View All Answers
What is mrp (material requirement planning) and what is the transaction code to access mrp list?
What are the essential components in sap mm?
What do you mean by the release procedure?
What is a profit center?
What is the procedure to make the period indicator in the mrp2 view as āpā?
How will you configure a class type?
The material does not have a master record. How can we procure that?
Explain the 'accounting' side of gr?
A stock transfer was done between two plants belonging to same company code and between two plants belonging to different company code. What will be the difference between the two?
What are the procedure to create pr or po by mrp?
How you can link a document to a vendor master record?
What are the data in material master that are maintained at the company code level?
What is vendor evaluation and how do you maintain it?
What are the important fields in purchasing view?
What is a purchase order?