I am an electrical power engineer and arranged power system
for a data center, I installed MCB, ELCB and erthing system
TN-C-S.
But some times several ELCBs Disconnect circuits at the
same time! what may be the reason? (the ELCBs are 25A ,30mA)
Answer Posted / chandra
Mr. Mehdi, Do check the neutral of all circuits wether they
are connected to same ELCB group. If one neutral from one
group is connected to other group this problem will occur.
Even though all neutral is common at final point, each
neutral will have to pass through the ELCB in order to
monitor the return cuurent.
Is This Answer Correct ? | 10 Yes | 0 No |
Post New Answer View All Answers
Please provided formula for calculate the cable size from step up transformer to M.V panel, run overhead aluminum cables, total load is 5mega watt, total length 900 feet.
what is the minimum winding resistance of 30hp compressor, to run or to switch on
There is any especial requirement for motor to drive through with VFD?
how many electricity poles are there and what are the names and their sizes.
How much voltage we need to apply in 33kv cable during hipot test of cable
If 100 KAV USP dedicated earth got disconnect / Cut. What will happen at load.
What is difference between start imitation and start interlock for 3 phase motor protection ?
what is physical distance of isolator to VCB in 33/11kv sub stations
what is sevice settings for mccb?How can be it setted?
What is the most important precaution in any experiment with d.c. Shunt motor?
What is essential to prove safe isolation of electrical circuit?
how much flux density of CRNO core
hi, could someone help me to find a control design for syncronising panel .
Difference between transition and diffusion capacitance
How do i perform grounding of star point of Genset (400V) for making connection with step up transformer of DELTA-DELTA (400V to 20KV) ? while Genset itself has its own neutral and grounding bus bar inside genset breaker box whereas we have another neutral and grounding busbar in synchronizing panel next to genset at maximum distance of 6meter, would someone pls advice if we can only perform neutral grounding in synchronizing panel or should we ground neutral on both places inside genset breaker box and synchronizing panel.