Method of findingthe dry ingredient quantity of 1 m3
concrete.
Answer Posted / naresh thakur
soppose, concrete mix ratio = 1:1.5:3
then, sum = 1+1.5+3 = 5.5
as we know,dry material required for 1 cum. of concrete =
1.54 cum.
then we can find -:
(1) cement = 1*1.54/5.5 = .28 cum. or .28cum.* 28.8= 8.06
bags.
(2) sand = 1.5* 1.54/5.5 = .42 cum.
or .42cum.* 35.3 = 14.83 cubic feet.
(3) coase aggregate = 3* 1.54/5.5 = .84 cum.
or .84 cum.* 35.3 = 29.65 cubic feet.
so, dry ingredient quantity required for 1 m3 of concrete-:
cement = 8.06 bags.
sand = 14.83 cft.
coarse aggregate = 29.65 cft.
do not forget to add 5 to 8 % addition matreial.
Is This Answer Correct ? | 345 Yes | 36 No |
Post New Answer View All Answers
What is the maximum crushing load in Kg & crushing strength in N/mm2 for M25 & M 15 Grade concrete
what is tension footing?
what is meant by shear center?????
what is thumb rule for calculating the size of ISMB required for a particular length of span
What are the disadvantages while using stone dust as filler in pavements?
Why Is Propping Required For Long Structures Once The Form Work Is Removed?
how can we construct building without foundation providing only grade beam at ground level
length where bent up is made in slab of bridge from one end
how to calculate the chair reinforcement length in slabs, footing or anywhere??
What is the thickness of slab for 600 sq each) 2 slab construction. What should be the size of steel rod?
density of crush sand & crush stone or grit powder
What is Architect-Prepared Contract?
can you mail me detailed procedure,entire syllabus and practice papers of mpsc civil engineering branch.I am in third year now
Can anyone suggest how to determine scheduling of reinforcement of floor beams from Staad model,other than clicking each beam respectively 7 noting down the values ?
What is the method of soil replacement test?