Suppose you did all your work in a 32 bit system, the
production server is 64 bit system, you find that during
UAT, the system fails and is not working, how will u
communicate to your customer, what solution will you
provide to the client?

Answer Posted / bj

Check back with your specifications regarding the server
requirements. If the requirement was never specified, you
have assumed that the requirement is a 32 bit system.

In this situation, list the possible reasons why it failed.
Run a system test on a 32 bit machine and doubly ensure that
the reason for failure in only the server specification

Schedule a meeting with the customer and let them know that
the UAT failed and the most probable reason being he server
specification. Provide them the list of other possible
reasons (if you found any) and also inform them about your
plans on how to plan to tackle the issue and your
guesstimate of the time for the same.

Based on the criticallity of the system, one of the
solutions could be to deploy the software system on a 32 bit
server while you figure out a way to fix the issue. This
option could be given to the customer.

It is quite possible that the customer would take this
option and this would save time for the customer and help
your team to quickly find a fix.

Otherwise go with whatever the customer thinks you should do.

Is This Answer Correct ?    19 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

You need to convey some very complex, detailed information to the project stakeholders. The best method of communicating this kind of information is? A. Verbal B. Vertical C. Horizontal D. Written

536


You are a project manager working on contract. You’ve performed earned value analysis and discovered that the project will be completed on time and under the original estimated amount. This means the profit to your company will decrease as will your personal bonus. Which of the following should you do? A. Add activities to the project to increase the cost enough to meet the original estimated amount. B. Tell the customer you're adding additional requirements to the project chat were originally cut because of cost constraints. C. Inform the customer that the project is completed and has come in under budget. D. Bill the customer for the full amount of the contract as this was the original agreed-upon price.

581


You are preparing a cash flow analysis for a project the company is considering undertaking. The project's cost is $525,000, and expected cash inflows are $125,000 the first year and then $75,000 per quarter the second year and $100,000 per quarter after that. What is the payback period? A. 16 months B. 27 months C. 32 months D. 28 months

627


You are a project manager for Cashiers systems. Your company produces cashiering systems and software for the retail industry. Your customer has requested a change to the product. You will handle this change using the scope change control system. All of the following are true except: A. Changes to product scope should be reflected in project scope. B. Project scope changes may result in adjustments to the performance measurement baselines. C. Changes to project scope should be reflected in the product scope. D. Scope changes may result in performance improvements.

550


A project is considered successful when: A. The product of the project has been manufactured. B. The project sponsor announces the completion of the project. C. The product of the project is turned over to the operations area to handle the ongoing aspects of the project. D. The project meets or exceeds the expectations of the stakeholders.

626






You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the company. Your lead engineer has given you the following estimates for a critical path activity: 60 days most likely, 72 days pessimistic, 48 days optimistic. What is the expected value, or weighted average? A. 54 B. 66 C. 60 D. 30

708


What are the outputs of the Performance Reporting process? A. Performance reports and change requests B. Performance reports and other project records C. Change requests and performance reporting D. Change requests and performance measurements

571


You are a project manager for a manufacturing firm that produces Civil War-era replicas and memorabilia. You discover a design error during a test production run on your latest project. Which of the following is the most likely response to this problem? A. Reduce the technical requirements so that the error is no longer valid. B. Go forward with production and ignore the error. C. Go forward with production but inform the customer of the problem. D. Develop alternative solutions to address the error.

698


You are a contract project manager working with the State of Bliss. Your latest project involves rewriting the Department of Revenue's income tax system. As project manager, you have taken all the appropriate actions regarding confidentiality of data. One of the key stakeholders is a huge movie huff, and she has the power to promote you into a better position at the conclusion of this project. She's reviewing some report data that just happens to include confidential information regarding one of her favorite movie superstars. What is the most appropriate response? A. Report her to the management team. B. Request that she immediately return the information, citing conflict of interest and violation of confidential company data. C. Do nothing as she has the proper level of access rights to the data and this information showed up unintentionally. D. Request that she immediately return the information until you can confirm that she has the proper level of access rights to the data.

511


What are the different types of software risks?

516


Which of the following processes negotiates the sequence of award by rank ordering the proposals? A. Source Selection B. Solicitation C. Contract Administration D. Procurement

679


You are a project manager for Dutch Harbor Consulting. Your latest project involved the upgrade of an organization's operating system on 236 servers. You performed this project under contract. You are in the Contract Closeout process and have reviewed the contracting process to identify lessons learned. What is the name of the tool and technique of Contract Closeout you used to perform this function? A. Procurement audits B. Performance reviews C. Performance audits D. Procurement reviews

657


You are the project manager for Changing Tides video games. You have gathered the inputs for the Activity Duration Estimating process. You will employ which tools and techniques to produce the outputs for this process? A. Activity list, analogous estimating, quantitatively based durations, and alternatives identification B. Activity list, analogous estimating, expert judgment, and quantitatively based durations C. Expert judgment, analogous estimating, quantitatively based durations, and reserve time D. Expert judgment, alternatives identification, quantitatively based durations, and reserve time

722


You are a project manager for Dakota Software Consulting Services. You're working with a major retailer that offers their products through mail-order catalogs. They're interested in knowing customer characteristics, the amounts of first-time orders, and similar information. The stakeholders have accepted the project scope. Work has begun on the project, and you're confirming some of the initial work results with the stakeholders. You've asked for acceptance of the work results. Which process are you in? A. Quality Assurance B. Quality Control C. Scope Verification D. Performance Reporting

767


Your upcoming project includes project team members from a foreign country. In order to make certain that cultural differences don't interfere with team performance, thereby affecting the success of the project, your first course of action is to do which of the following: A. Provide diversity training to all the team members. B. Collocate the project team. C. Perform team-building exercises. D. Inform the team members of the organization's rules and standards.

700